Error in WBS element while doing the purchase requisition

former_member324037
Participant
0 Kudos

Dear All,

While doing the purchase requisition in ps

the error is : Item 010 WBS element IN05-PR09-16 . 04 budget exceeded.

Kindly parovide any solution.

Best Regards,

Venkat.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Venkar,

Check the available budget against WBSE - IN05-PR09-16 . 04 (S_ALR_87013558 - Budget/Actual/Commitment/Rem Plan/Assigned ), and the PR amount. Available Budget should be more than PR amount. Based on the tolerance limits set for the budget profile, maintain the Current Budget with budget updates and try to create a PR accordingly.

Hope this solves your problem !!

Br

Hari.

Edited by: Hari Krishna Kudaravalli on Aug 20, 2009 3:25 PM

Answers (1)

Answers (1)

raghavendra_praveen
Active Contributor
0 Kudos

Hi

In addition to above ( checking the available budget in S_alr_87013558) you can also check available budget in S_lar_87013561 or in CJ33 (difference between release and assigned values). Also note that budget should be released in the fiscal year in which you are creating the PR (check the delivery date).

Thanks