AUC settlement rule

Former Member
0 Kudos

Dear All,

Currently we have configured the system by specifying the AUC settlement rule in WBS level. Can we do this Cost element level and how?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

cost center wise is possible not for cost element wise

Answers (1)

Answers (1)

stheurkar
Active Contributor
0 Kudos

Hi,

You can maintain settlement rule for following valid receivers......not possible for cost element.

G/L account

Cost center

Order

WBS element

Fixed asset

Material

Network

Profit. Segment

Sales order

Cost objects

Order Item

Business proc.

Real Est. Object

Regards,

Sandeep

Former Member
0 Kudos

Thanks AP and Sandeep for the replies.

If Iu2019 am to rephrase the question as u201CCurrently in investment projects AUCu2019s are being created at WBS level. Can we create AUCu2019s at cost element level?u201D

Appreciate your assistance.

Former Member
0 Kudos

hi

no you cannot.

stheurkar
Active Contributor
0 Kudos

Hi,

No......it's not possible.

Regards,

Sandeep

Former Member
0 Kudos

Hi,

Many thanks again for the prompt replies. One final question -In investment profile what is the use of the

"AuC per source structure/assignment" flag?

Former Member
0 Kudos

Hi Romesh,

If you want to settle the amount debited on the WBSE (investment measure), separately by cost elements to various assets under construction, you need to tick this check box in Investment profile. For this you have to maintain a source structure with several source assignments, each of which contains the individual cost elements or cost element intervals to be settled using the same distribution rules. This Source structure is to be assigned in the Settlement profile.

Hope this clears you !!

Br

Hari.