on 08-19-2009 7:14 AM
Hi,
I created a project assigned budget to it. Carried out CJCO run. Now i want to reverse it all and want to attach this project to IM structure. How do i do it?
Hi,
As far as i know the standard SAP documentation says that CJCO does the reversal in special cases such as when there is a shortage of budget in the sender fiscal year. But i have not tried this yet .
One way can be return budget from projects , T-Code : CJ35 or
try this below mentioned thing
Goto T-code: CJCO and enter =REVERSE_ON in the command field means the field where you put your t-code.
Try this ..........
Thanks ,
Dhruv Kumar Malhotra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Step1: Tcode CJ34, enter the sender Year, enter the receiver Year
Step2: Enter, and mention the Receiver WBS Element and the Sender WBS Element as same, mention the Amount to be returned along with the Currency.
Hope it helps....
Thanks!!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.