on 08-18-2009 4:12 PM
Hi All,
My client has the scenario at one warehouse location that they already use SUM. Is it possible to use a combination of SUM and HUM in the same warehouse and same storage types, they have mixed storage for the two different business scenarios.
Do I assume correct that if HUM was at single level and not nested SUM and HUM would work OK together as HUM is at IM level and in WM the HU's become SU's anyhow.
I would appreciate your thought and advise, potential issues etc.
Thanks
Stuart
Hi,
Yes HU at IM level will be identified in WM as SU. Inside WM all HU will be handled as SU. Hence i do not see any problem or potential issues.
Regards,
Jothiswaran.