on 08-18-2009 11:48 AM
Hi,
I am using 3 Nos. of 2nd Level WBS elements for 3 company codes. The 1st level is having project currency USD.
The WBS values are 200 INR, 100 EUR and 300 USD respectively. The cumulative value is shown as 600 USD which is not correct.
All are costs taken from internal activities only.
I get the following report in Project planning board and in S_ALR_87013533 for planned costs.
P-001 - 600 USD
P-001-01 - 200 USD
P-001-02 - 100 USD
P-001-03 - 300 USD
I have maintained exchange rates. I am able to see the converted values in cost report when viewed from EDIT menu in CJ20N for individual activities only.
Please suggest how to get the converted values in planning board and S_ALR_87013533 reports.
Thanks,
Kabir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.