I´m currently testing the integration between MSProject and cProjects 4.0. I´m currently importing an MSProject to cProjects but I have a question.
When I create a project in MSProject with a milestone that has 0 days duration, and import that project to cProjects, the duration for that milestone in cProjects appears with 1 day duration.
How do I make the milestones appear in cProjects with 0 days duration?
Thanks and best regards,
Fernando Montenegro
Hi
Im afraid but i think 0 day activities are not possible.
Let the duration of Task be 1 day you can have efforts 0 hours
Niranjan