MS Project import - Milestones

Former Member
0 Kudos

Hi experts,

I´m currently testing the integration between MSProject and cProjects 4.0. I´m currently importing an MSProject to cProjects but I have a question.

When I create a project in MSProject with a milestone that has 0 days duration, and import that project to cProjects, the duration for that milestone in cProjects appears with 1 day duration.

How do I make the milestones appear in cProjects with 0 days duration?

Thanks and best regards,

Fernando Montenegro

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Im afraid but i think 0 day activities are not possible.

Let the duration of Task be 1 day you can have efforts 0 hours

Niranjan