User Exit at the time of activity saving

Former Member
0 Kudos

Dear all,

I want to update activity constarints & date based on some logic & want to ensure that at the time of activity saving logic should triggered. I want to use user exit for this.Validation/ substitution is also one option but does not seem feasible. if you know any user exit at the time of activity saving, please share with me.

Regards,

Ashok Sangal

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi ,

Check user exit PPCO0007.

Thanks

Saikishore.Ganga

Former Member
0 Kudos

Hi Saikishore

Thanks for prompt reply..

This exit is for Production order, whteher this will work for Project activities, I mean , will this be available in CJ20N?

Regards,

Ashok Sangal

nitin_patoliya
Active Contributor
0 Kudos

You requirement is to check the constrain based on scheduling . THere is not user exist I believe that may exaclty address your requirement. THan also check below two user exit.

CNEX0028 Check activity release

CNEX0029 Check network release

Ideally yhou should chekc for hte some BAPI for hte network save will help you .

Regards

Nitin P.

Former Member
0 Kudos

This message was moderated.