hi,

When i was trying to raise a sales order,an error message appears

Assign a controlling area to company code 8888

Message no. KI200

Diagnosis

Cost accounting is active for company code 8888 but no controlling area has been assigned.

System Response

Postings where cost accounting is active can only be made after a controlling area has been determined.

Procedure

Either

deactivate cost accounting in company code 8888

assign a controlling area to company code 8888

Both of these operations are done via the configuration menu.

i have removed the controlling area ,but the same message reappears.I request you to kindly help me in this regard.

Regards,

Phani Prasad

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

I took the help from my fi colleague.Thanks for your suggestion.

Regards,

Phani Prasad.

Former Member
0 Kudos

Hi,

Check you setting in OX19.

Here you can remove the company code from the controlling area.

Or you can assign the company code to the controlling area.

Just check your setting over here and let us know.

Regards

Raj.

Former Member
0 Kudos

hi,

The following message is appearing

Groups still exist in controlling area 8888 .

Message no. KT307

Diagnosis

You want to delete controlling area 8888, although groups still exist: 01018888BUS_AREAS (group type Cost Centers).

Procedure

Delete all groups for controlling area 8888.

Regards,

Phani prasad.

Former Member
0 Kudos

Hi,

Go to OX06 and check whether controlling area 8888 exist or not.

If you will see the controlling area 8888 then delete that entry.

Regards

Raj.

Former Member
0 Kudos

Hi

Could not delete my controlling area .The same message appears.

Regards,

Phani prasad.

Former Member
0 Kudos

Dear Phani,

Delting Cost center is not an easy task, it may impect the other areas also. It require analysis from the FI perspective and thus the involvement of FI consultant is must. anyways for the error which you are getting, you can check

KAH2 - Change Cost Element Group --> by using this t-code you can select the nodes related to Cost center and can delete that first.

KSH2 - Change Cost Center Group--> By using this t-code you can select the cost center group node and delete.

I will again recommened take the help of FI for further analysis,