on 08-14-2009 3:33 PM
I have a similar problem as the poster Vaibhav Modi had, but I have a bit of a difference that is causing my issue.
I have two companies in E-Sourcing. The Enterprise company has the contract generation phases available and we can create contract doc templates within the Enterprise company. Our problem is that the second company does not have the phase configution nor is the Library Item Phase Configuration even an option in the Setup menu.
How do we get the phase configuation for the contract generation available to the second company?
Thank you for any assistance.
Elizabeth
Hello Elizabeth,
Upload workbook "Sourcing_Company_QuickStart.xls" with the user of second company. It will solve your problem.
~Ankush
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This worked perfect. Cannot believe I did not think of it.
Thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This worked perfect. Cannot believe I did not think of it.
Thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I will giive this a try and respond back.. Thank you very much. (Seems so logical, that I feel silly, not thinking of it.)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I will giive this a try and respond back.. Thank you very much. (Seems so logical, that I feel silly, not thinking of it.)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.