on 08-14-2009 4:32 AM
Hi experts,
Does anyone know how to change the default date in person assignment tab in cj20n? Currently, the system always take the scheduled finish date to the date of the person assignment tab. Can I change it to the start date?
Thanks and rgs,
Michelle
Hi Michelle,
Goto SPRO->Project system->Dates->Scheduling->Specify Parameters for Network Scheduling, Here you can control the workforce planning dates.
Hope this is useful...
Regards
Aatish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes you can chagne it.
With regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am not exaclty able to tell from where it picks the date, just sharing with you my understading. Normally persona assignment tab appears for hte activit in cj20n after you give workcenter / work filed in the activity . So, from work center master data seeting / capacity seetings these date mostly will originate.
With Regards
Nitin P.