SAP APO PP/DS - default heuristic used when using SAP_MRP_001

Former Member
0 Kudos

I am using APO PP/DS release 5.1

When running the control heuristic SAP_MRP_001 for production planning, one can specify that the planning heuristic to be used for a given product can be taken from the product master, or from the heuristic defined on the settings for SAP_MRP_001.

But if neither of these are set, how is the 'default' planning heuristic determined.

I cannot see this defined in the 'global settings' for PP/DS.

Thanks,

Bob Austin, Atos Origin

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Austin,

Apart from product master and heuristic setting in customisation, you can also define your PPDS

heuristic setting during PPDS planning run using transaction /SAPAPO/CDPSB0.

You can set your heuristic and save as variant.

This variant will be called when you are executing transaction /SAPAPO/CDPSB1.

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Senthil,

Thanks for your rapid response!

My question remains though, I think.

If for a production planning run, one specifies SAP_MRP_001 for a given product, and if there is no planning heuristic specified for the product on the product master, then what default planning heuristic will be used?

I think the answer is SAP_PP_002 (planning by standard lots), but I cannot see this default actually defined in SPRO.

Thanks, Bob.

Former Member
0 Kudos

Bob,

Default heuristic comes first from the Product master (which you already know). If this is not populated, then the default drops down to the Planning Procedure. IMG>Supply Chain Planning>PPDS>Global Settings>Maintain Planning Procedures.

Rgds,

DB49

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Austin,

If you select SAP_MRP_001 heuristic in production planning run, the system does

Product Planning (Comp. acc. LLevl Code) which is based on the algorithm

/SAPAPO/HEU_MRP_PLANNING.

Whereas as you specified, the heursitic SAP_PP_002 uses the logic

Planning of Standard Lots with algorithm /SAPAPO/HEU_PLAN_STANDARDLOTS.

The settings for both the heuristic are different.

Hence based on the heuristic that is selected (if say SAP_MRP_001, it will

execute its algorthm only), the heuristic function will be used for planning

Regards

R. Senthil Mareeswaran.