How it is possible that when we post the budget in CJ30 against any WBS that will reflect in corrospondant Fund Center / Cost Center in Fund Management.
You are confusing two different budgetting functionalities. CJ30 has nothing to do with Funds Management, so will not be reflected in FM.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
There is two type of budget control on at the commitment level where the fund management should be activated and project cash management should also be activated.
But for cj30 budget planning and controll fund management and cash management not needed.
Sukhveer.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The case is that the Cost center is mapped with Fund center i.e. itegration of Fund managemnt and Contolling and that cost center is assigned to WBS element. Now i wish that when i postthe budget in wbs element through CJ30, it will reflect in corrospondent Fund Center.
How it is possible?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.