on 08-11-2009 4:56 PM
Hi
I am upgrading a Windows 2003/MS SQL 2005 sandpit NW04 BI 350 dual stack (ABAPJAVA) to BI7 (NW04S ABAPJAVA) as a test before working on our actual landscape, I have started the ABAP upgrade and chose the 'resource minimised' method as downtime isn't an issue on the sandpit, I then started the upgrade on the Java stack, but then noticed in the documentation it states you should use 'downtime minimised' for a dual stack upgrade? the ABAP prepare recognised I had a dual stack and said it would be synchronised but never complained about the resource minimised choice ? the phases have been waiting for synchronisation so far without a problem.
Is this a problem? I can reset the upgrade, but its quite far through, so would rather not !
Thanks,
Paul.
Hello Paul
As you said, SAP state that you must perform a dual stack upgrade using strategy downtime - minimised. I had a problem when I used resource minimised but if your upgrade is running then donu2019t terminate it. If it works, thatu2019s great.
What I normally do is run strategy downtime minimised with an import time of zero hours.
Thank You
Anwar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Anwar
Thanks for the response, the upgrade completed successfully, I will remember next time to use the downtime minimised option !
Paul.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
10 | |
9 | |
8 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.