Costing for BOM

Former Member
0 Kudos

Hi,

I have a BOM that consist of Material A and Material B.

I have assigned the BOM as a material component to the network activity.

Currently the cost is getting from the standard price of the BOM material itself.

Is is possible that the cost is the sum of the total value of Material A and Material B that is assigned to the BOM?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Create a header material (only with basic data, general view maintained) and assign all the components with reference point , then transfer BOM using CN33 transaction to project structure. all the components will be assigned to the activities based on the reference point maintained in activity.

Now when you generate cost report this will give you the total cost at WBS level for all components assigned to it.

Hope this helps

Thanks,

Srihari.G