on 08-11-2009 5:23 AM
Hi gurus,
Is it possible to transport tasks from QAS to PRD when DEV system is down and Domain Controller at DEV....
Thanks in advance.....
Regards,
BBR.
No you cant .
Domain controler is the central system that takes care of transport .if your domain controller is down you cant move any transport.So always recomeneded that to make the domain controlller that system which has the leaset down time that is production.
Thansk
Rishi Abrol
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.