Hi,
I have created an internal activity without any work hours or workcenter and saved. I assigned a material for that activity the system generated PR for that material, when i go to commitment report the value of that material for the specified qty is not comming in the report. The system is showing showing the material value as plan cost. Can any one please help me out why the value is not comming in commitment report.
Thanks
Satish.
Hello Satish,
Please check price/currence in Purch.data tab of component. if this is not maintained the cost cannot be calculated , so the commitment is not shown.
hope this helps.
Thanks,
Srihari.G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In the network header control tab check "Res./Purc. req." field is set to "3 Immediately" .
rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.