on 08-08-2009 9:53 AM
Dear all,
Two questions:
Q1 - For some reason when I try to perform result recording using QE11 (i.e. record result with inspection point), system complained that u201CNo inspection point available for the operationu201D when I hits the u201CAssign Insp Pointu201D button.
Q2 u2013 Why system asks for physical sample on a pop-up box (i.e. inspection point) when I didnu2019t setup the physical sample drawing on the system?
The following are my setup in the system:
A u2013 Master recipe header;
uF0D8 Inspection point: 130- Inspection point based on container (Standard SAP).
uF0D8 Partial Lot Assignment: 2-Partial Lot and batch for each inspection point.
uF0D8 Sample Drawing Procedure: blank.
B u2013 Master recipe operation;
uF0D8 Inspection Point completion: Quantity, valuation and confirmation
uF0D8 Qty-related radio button: checked
uF0D8 Quantity Interval: 20 kg
uF0D8 Last Partial Lot assignment radio button: checked.
C u2013 MIC;
uF0D8 There are six MIC created and insert to this particular operation (FYI there are 5 individual operation in the master recipe). Two MIC are qualitative-relevant and sharing similar sample procedure, the other five are quantitative-relevant and sharing same sample procedure. Both of these sampling procedures are using u201CFree Inspection Pointsu201D.
D u2013 Physical Sample Drawing;
uF0D8 There is no setup on this as I still not know this topic
The inspection lot is created once I released the process order, and the fix sample size is showing in the lot.
Thanks.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
At header change Partial lot & batch for each inspe point to partial lot for each inspection point
during valuation batch will not occure
Regrads
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sujit,
My material is batch-managed.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
Have your material batch managed.
if not then at header change Partial lot & batch for each inspe point to partial lot for each inspection point.
I hope this may help
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.