Dear experts,
after doing a Post goods issue, system is not picking project stock but it is picking storage location stock (normal stock)
(in MB1B this project stock is created with a movement type 561Q)
(in sales order WBS is put at the item level.)
please give solution
atul
Hi
This is because of the simple reason that when the sales order is created your item category (which is getting determined in sales order) has not been marked with special stock indicator as Q while order creation
This is first mistake
(in MB1B this project stock is created with a movement type 561Q) As per my knowledge MB1B is transfer postings and movement type 561Q cannot be used here
This is Second mistake
Pls mark your sales order your item category with special stock indicator as Q and then create sales order
Make proper reservatation with proper t code movent types (take the help of MM people)
Stocks should show as Project stocks separately in your plant in MMBE
Then create delivery and do PGI
That Project stock in MMBE will be consumed for this PGI so general unrestricted will remain same
Regards
Raja
Edited by: ramanathan raja on Aug 8, 2009 11:38 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Atul,
You need to create project stock by using movement 412 Q in MIGO with ref. to WBS element after you allocate material to Network Activity in PS.
Then you can create del. doc. by using CNS0 and giving ref. of Project definition
Hope it will solve your problem
regards,
Sagar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sankar,
Why to make apt as service material. Instead make Apartment as finished goods (FERT mat. type).
Use milestone billing with item category TAO.
Make it order related billing.
Create WBS element in PS. Create milestone under WBS element that will tell about how much to bill and also how project is completed in terms of % and copy the same mile stonestone in sales order by assigning the WBS element in Account Assignment tab in line item.
Kindly post your feedback
regards,
Sagar
Hi Atul
have u tried doing deliver with Tr. CNS0.
please write what eaxct error u r facing.
Regards
Mandar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.