VL04 transaction for creating the delivery

Former Member
0 Kudos

Dear Guru's

we are doing STO process for some materials from plant 1 to plant2.

for example i have made po for 100 nos.

if there is only 30 nos in stock then when we do VL04 system will create delivery for 30 nos.

this process was running fine from two years but now we are facing problem that,

when i do VL04 system is creating two deliveries.

for example stock is 40 nos then system is creating delivery for 24 nos & 16nos.

please help to resolve the problem.

Regards

prakash

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

not answered

Former Member
0 Kudos

Hello,

This is nothing because of DELIVERY SPLIT, please check the following whiich causes the delivery split

SHIP TO PARTY

SHIPPING DATE?DELIVERY DATE

INCO TERMS

DIFFERENT ROUTES

DIFFERENT PLANTS/SHIPPING POINTS

please check the above criterial for the deliveries which were split

cheers,

santosh

Former Member
0 Kudos

did the system create 2 delivery items in the sam delivery?

then check if TVSHP-EXIDV_UNIQUE was switches ON recently (e.g. for HU-Management)

System then behaves totally different regarding requirement determination => check OSS

cheers

carsten