on 08-08-2009 7:07 AM
Dear Guru's
we are doing STO process for some materials from plant 1 to plant2.
for example i have made po for 100 nos.
if there is only 30 nos in stock then when we do VL04 system will create delivery for 30 nos.
this process was running fine from two years but now we are facing problem that,
when i do VL04 system is creating two deliveries.
for example stock is 40 nos then system is creating delivery for 24 nos & 16nos.
please help to resolve the problem.
Regards
prakash
not answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
This is nothing because of DELIVERY SPLIT, please check the following whiich causes the delivery split
SHIP TO PARTY
SHIPPING DATE?DELIVERY DATE
INCO TERMS
DIFFERENT ROUTES
DIFFERENT PLANTS/SHIPPING POINTS
please check the above criterial for the deliveries which were split
cheers,
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
did the system create 2 delivery items in the sam delivery?
then check if TVSHP-EXIDV_UNIQUE was switches ON recently (e.g. for HU-Management)
System then behaves totally different regarding requirement determination => check OSS
cheers
carsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.