Hi All,

What exactly is meant by remaining order plan and does the system calculates it.We are using WBS with networks and PR's are raised through PS.When I see any heirarchy report for budget/actual/assigned/available,I see values in remaining order plan column which I am not able to verify.It is consuming the budget,how can this be reduced.

Also,is there any report which shows from where the remaining order plan is originating?

Regards,

MTH

Accepted Solutions (0)

Answers (1)

Answers (1)

Paulo_Vitoriano
Active Contributor
0 Kudos

These are order commitments. You can check OSS note 99572 to get inside the forms definition used in the report.