Hi All,

re: Access Enforcer Request: control of field "User Validity Start Date" and "User Validity End Date" v5.2+

Is there any way to control this field? We have noticed that it overwrites the existing fields on a user master record when a change user request is provisioned.

Thanks!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Gary,

There is no way to control this field as far as I know. Can you open a message with SAP and see the reaction?

Regards,

Alpesh

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi All,

SAP has responded with the following: "the fix has been targeted for the next support pack for GRC-SAE 5.3 SP11 and other relevant versions. The tentative release date of the mentioned Support Pack is in the month of April 2010."

Thanks,