BOM explosion for component in ECC which are relevant for planning in APO

Former Member
0 Kudos

Hi ,

as we assign materials the MRP type X0 with the MRP procedure X (without MRP, with BOM explosion) which are relevant to APO, so if i have BOM under this item then how this below level Items will be plan in ECC....?

as we are excluding the component from planning so how the below level will be plan .....?

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Ritz
Active Contributor
0 Kudos

Dear SCM APO 22 ,

Answer lies in your question only.

as the assembly is relevant to be planned in APO but it will be exploded in MRP and the lower level component will be planned in R/3 only if required.

Only teh assembly which have MRP type X0 will be planned in APO.

Revert back if you need further clarification.

Hope it helps you.

Regards

Ritesh

Former Member
0 Kudos

Ok Thanks .

Closing

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi SCM APO 22,

For items not defined in APO, you need to run separate MRP run

in ECC and those will be controlled through ECC and APO will

not plan those items

Hope it is clear now, please confirm

Regards

R. Senthil Mareeswaran.