on 08-06-2009 2:42 AM
Hi,
I have created a settlement rule at project level or top level WBSe, now when I am going to lower level WBSe, it has been inherited the same settlement rule created at project level. I am not sure whether it is standard functionality or am I missing something here?
Appreciate your quick response?
Cheers!!
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you manintain settlement strategy in SPRO then system will copy the settlement rule form superior WBSE. check it in SPROPSCOSTSAutomatic and periodic allocationssettlementsettlement for WBSEdefine strategy.
This is a optional functinality in SAP and defined in the customising as per our business requirement.
Regards,
Nag.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
10 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.