on 08-05-2009 8:26 AM
Dear All,
For studying capacity evaluation and work center load in my project I am going through various reports like:
1. From the Project planning Board.
2.Load evaluation work center view -
>CM01
3. Overload----->CM05
4. Variable view -
> CM07
5. With WBS element -
> CM53
However the most helpful are CM07 and CM53.
In these reports for a particular week in my project Remaining Available Capacity is shown Negative as there is an overload in this period. To get a better picture I will go with some Datas in the three cloumns being displayed.
1. Remaining capacity req -
> 330 HR
2. Available capacity in WC -
> 90 HR
3. Remaining Available Cap -
> - 240 HR
In my WC I have defined 9 HRS of work for 2 individuals and so the total capacity for a single day is 18 HRS. For 5 remaining days in this week it is 18*5=90 HRS.
My clients requirement is how many more individuals are required to be assigned in this WC so that there is no overload. And there should be a seperate column in this report which will display this.
However I think this can be calculated manually and the answer is -240/90 i.e 2.666 i.e if I assign 3 more persons then overload will be removed for this period. Right?
Correct me if I am wrong in my logic. Anybody can help how to meet my requirement then if I am right to add such a column in the standard reports with the help of an ABAPer.
Or can I do it by other means.
Suman
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.