Procedure for Clearing Open Transfer Requirements & Posting Changes

Former Member
0 Kudos

Dear All,

With my present SAP System, both IM & WM Stocks are zero for a given Sales Order / Line item. But there are pending Transfer requirements & Posting changes due to the fact that the users have not completed up until the TO Confirmation Stage. Now that the stocks are in harmony in both IM & WM, what do we do to the open transfer requirements and posting changes. What is the best practice procedure for the above scenario.

Appreciate an advice for the above scenario

Thanks

Shabeen Buhary

Accepted Solutions (1)

Accepted Solutions (1)

former_member536836
Active Contributor
0 Kudos

Hello,

Write a program which will call transaction LB02 for TR & LU02 for Posting change notice (PCN).This program will make status of these TR & PCN complete.

I already used the same.

Regards

Prashant

Former Member
0 Kudos

Dear Prashant,

Thanks a lot.

Regards

Shabeen Buhary

Answers (0)