on 08-03-2009 6:18 PM
Hi Experts - We are currently upgrading our ERP system to ECC 6.0 EHP 4.
Our middleware layer is a SAP PI 7.0 in SP12.
Are there potential conflicts between these two? Maybe around Proxies?
My current understanding is that SAP PI isn't closely coupled with the ECC system (we mainly use IDocs, some Proxies),
so there shouldne be any issues.
Do you have a different view or experiences? Thanks for your help.
Best Regards, Mathias.
Hi - Thanks for this hint.
I've also found two related SAP Notes on this that seem to reconfirm my assumptions.
0000954820 and 0001043047
However I'd also appreciate any experiences from your side.
Mathias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Mathias,
I would suggest to go through the upgrade document to get the exact issues if any are there:
http://service.sap.com/instguides -> SAP Business Suite Applications -> SAP ERP -> SAP ERP 6.0 -> Upgrade. Then select the OS and Database.
Regards,
---Satish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
10 | |
10 | |
9 | |
7 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.