05-05-2006 7:30 PM
Dear people,
Do you know if there is a user exit (or another thing) that works before the schedule line tab for an item of a sales order is displayed.
Specifically the functionnality we are developping is:
We are creating SCH line in the standard tab
Then in Aditionnal Data B (item) the schedule lines entered are displayed
User fill aditionnal data related tio the SCH line in Aditionnal data B
We need that the data previously entered in Aditionnal data B overwrites sch lines values and display the shedule line grayed (<u>on line will be great)</u>Thank you for any help you could provide.
Best Regards
Maximiliano
05-05-2006 7:34 PM
Check include MV45AFZZ. This a common user exit for VA01/02/03.
As far as I know, you can't gray out the Sch Lines in the standard tab, unless of course you go for a screen modification, but probably can update with the data from Add Data B Screen.
05-05-2006 7:34 PM
Check include MV45AFZZ. This a common user exit for VA01/02/03.
As far as I know, you can't gray out the Sch Lines in the standard tab, unless of course you go for a screen modification, but probably can update with the data from Add Data B Screen.