on 08-03-2009 11:08 AM
Hi Team,
What are the settings required for QM in procurement. I have set indicator for QM in procurement in QM view in material master.
I am not clear about following fields to be maintained in QM view.
QM Control Key
Certificate type
Target QM system
Tech. delivery terms Indicator.
Please suggest me in which case to be used this fiels. Is it relivant to Quality Certificates.
Thanks
Hi,
All meaning are
QM Control Key :
If you activate the indicator for QM in procurement in the material master record at the client level, you must also store a control key at the plant level for quality management in procurement.
Certificate type :
Certificate types applies to the Certificate processing in procurement & Certificate creation
Target QM system :
whether the vendor's verified QM system, according to vendor master record or quality info-record (for a combination of vendor/material) meets the requirements for QM systems as specified in the material master
- If you activate the indicator for QM in procurement in the material master record at the client level, you must also store a control key at the plant level for quality management in procurement. If you want Procurment control then accordingly define Control Key.
- If you want Vendor's perticular certificate for Material then you have to define Certificate type.
Also, you have to maintain Material, Vendor's Info record at plant level.
Thanks,
JM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.