HI Experts,

we have a SC with status Follow-on document(s) not transferred but when i checked the SC followon documents are created but the status remains as Follow-on document(s) not transferred.

How can i make this disappear from monitoring of SC.Is there any FM to perform the same

kindly suggest

regards

subbu

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks for the help

peter_novoth
Employee
Employee
0 Kudos

Hi Subbu,

please see also the note 865797.

Regards,

Peter

Former Member
0 Kudos

Hi Peter,

Corrections suggested in SAP note are already a part of the program.

Is there any FM to change the status bye executing it

regards

subbu

Former Member
0 Kudos

hi Experts,

Is there any way i can resolve this.

Kindly suggest

regards

subbu

Former Member
0 Kudos

Hello Subbu,

Have you checked the follow on document is created in ECC?

Run the reports with your shopping cart number.

BBP_GET_STATUS_2: Update requirement coverage requests

CLEAN_REQREQ_UP : Interval for update check

This should help.

Thanks

Ashutosh

Former Member
0 Kudos

Hi Ashu,

i have done this earlier and now aslo(executing the reports) but i did not find any change.

yes,follow on docuemnt is created for SC.

It remains same in SC and also in RZ20 against Not transferred to backend.

regards

subbu

former_member183819
Active Contributor
0 Kudos

Hi Subhu

Hope you are in classic deployment

your PO will be created in ECC only.

update BBP_PD status here for your sc.

get status job brings the PO information to SRM.

br

muthu

Former Member
0 Kudos

Hi Muthu,

yes we have classic deployment.system has created a follow on docuemnt(reservation) in R3.

below is the status we have in BBP_PD for SC

EADER I1015 Awaiting Approval X

EADER I1021 Created

EADER I1038 Complete

EADER I1106 Shopping cart ordered

EADER I1129 Approved

000000001 I1111 Item in Transfer Process X

000000001 I1112 Error in transmission

000000001 I1113 Follow-on Document Created

000000002 I1111 Item in Transfer Process X

000000002 I1112 Error in transmission

000000002 I1113 Follow-on Document Created

Jobs are running fine with out any logs i ahve problem only with one SC.and user is behind me.

regards

subbu

Former Member
0 Kudos

I know this is vague but still can you check if there are any entries maintained in the BBP_DOCUMENT_TAB ??? If there are any entries try clearign the entries and also try executing the FM BPP_REQREQ_TRANSFER.

Hope this helps you!

Regards,

Kalyan

Former Member
0 Kudos

Hi Kalyan,

No it did not work.Thanks for the suggestion anyways

regards

subbu

Former Member
0 Kudos

Hi Subbu,

Did you check if there is any issue with the workflow ?? there could be multiple/duplicate work items created for this particular SC! Can you check in BBP_PD if there are any multiple work items for this SC ???

Regards,

Kalyan

former_member183819
Active Contributor
0 Kudos

Hi Subbhu

Eventually what is the stattus showing sc monitoring for 2 items in one sc

follow on document folder of sc

history .

Hope you can see reservatiosns what is the status here ?

....?

br

muthu

Former Member
0 Kudos

Hi Kalyan,

This Sc is having single level approval.There is no multiple or duplicate workitem generated.

i am not getting why the status remains same even after executing so many FM.

regards

subbu