on 08-03-2009 4:09 AM
Hi, we have to inspect the tool if it is used 100 times for production or if the inspection date expires 1 year. pls advise how to map this in pm? acccordingly we have to check the tool periodically. pls advise the steps.
Hi
1.Create a Equipment Master in IE01.
-->mension the work center & cost center of the equipement here.
2.Now create a Equipment task list either in IA01 or IA05.
-->remember the use of Inspection point & sampling procedure.
3.Now In IP01 schedule the equipment
-->attach euipment & Task list here.
mension the start of cycle.Inyou case say calibration frequency is say 1 yrs(inspection date expires 1 year)
then mension it here only.
Now in IP30 start the maintaince cycle.--->when you will issue the tool.
After one year Inspection lot will be created for this tool(maually or auto by scheduling).Inform the parties for due inspection.list of due inspection s can be seen in IP24.
I think this is the possible solution in this case.
Regards'
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.