Reservation for WBS

Former Member
0 Kudos

Hi Friends,

While transfer of material through B.O.M or creation of P.R , "Reservation of WBS"should be made default instead of "Resevation of Network". can we change the sequence, so that Reservation of WBS will come first and then Resevation of Network. Please reply...

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi prasanna,

You can control it using procurement indicator ( OPS8).

Assign that procurement indicator in Network Profile.

Regards,

Amit