Budget error - annual budget 2009 is negative

Former Member
0 Kudos

Hi, just want to ask the nature of this error when doing Budget Transfer (cj34) . " Annual budget 2009 is negative" . Knowing the fact that we dont maintain annual budget for the project. What should be done to correct this? thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member203108
Active Contributor
0 Kudos

This message was moderated.

Former Member
0 Kudos

hi , still the same error when processing even without value in sender and receiver year. the error is now Overall budget is negative. Thanks

former_member203108
Active Contributor
0 Kudos

This message was moderated.

Former Member
0 Kudos

Closing this thread.

Former Member
0 Kudos

hi ,

    how you deal with this question?  we have this question too.

Former Member
0 Kudos

budget already available for level 2 wbs (sender) but not yet distributed to lower levels of wbs, reason why we allocate the budget by doing budget transfer but encouter this error.

Former Member
0 Kudos

If you want to allocate budget from level 2 wbs to level 3 or 4 wbs in the same project definition, you can use CJ30 instead of CJ34

Former Member
0 Kudos

we preferred using budget transfer or budget supplement instead of changing the original budget. we wanted to retain the budget assign for a particular wbs.

Former Member
0 Kudos

Hi, Marnee,

Why don't you use CJ37 to make budget supplement(for overall budget)?

Thanks,

Atom