on 07-30-2009 2:41 PM
Hi,
I can see the Planned cost in S_ALR_87013532.It is material and labor cost. In which table can I see it?
Regards,
Hi,
Check Table COSS - Cost Totals for Internal Postings and COSP - Cost Totals for External Postings with Valuation Type , field : WRTTP =1 to get planned costs and actual costs with valuation type=4
Please check and confirm.
Regards,
Selva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For Plan Cost:
(1) In case of the manual Cost Planning for (WBS Elements): For Plan Cost of individual WBS; we should pass WBS as input to PRPS-PSPNR and obtain the PRPS-OBJNR. After fetching the PRPS-OBJNR, pass this value to RPSCO-OBJNR with value type RPSCO-WRTTP = 1 and get Plan cost for WBS by adding the value obtained in the following fields of RPSCO table WLP00, WLP01,...to.... WLP16.
(2) In case of the Network Costing: For Plan Cost of network activity (NWA); we should pass the network number to AFKO-AUFNR and obtain AFKO-AUFPL. Pass AFKO-AUFPL to AFVC-AUFPL and obtain AFVC-OBJNR (object number for NWA). After fetching the AFVC-OBJNR, pass this value to RPSCO-OBJNR with value type RPSCO-WRTTP = 1 and get Plan cost for NWA by adding the value obtained in the following fields of RPSCO table WLP00, WLP01,...to.... WLP16
Hope it helps...
Thanks!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.