on 07-30-2009 9:43 AM
Dear All,
why the material stuck in quality .if quality plan is made for these mtl
Thanx
N.K S
Hi
Go to QA32>check the status of the lot>If it is CRTD
then
Go to QA02>enetr lot number>select Inspection Specification-->click on Inspection specification
click on sample. & save
Now check the status is REL
Now in QA32 take UD.
(check the valid from date of Inspection plan it must be prior to lot creation date.)
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks & closed
Thanx
n k s
Edited by: Nand k singh on Jul 30, 2009 1:33 PM