Dear All,

why the material stuck in quality .if quality plan is made for these mtl

Thanx

N.K S

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Go to QA32>check the status of the lot>If it is CRTD

then

Go to QA02>enetr lot number>select Inspection Specification-->click on Inspection specification

click on sample. & save

Now check the status is REL

Now in QA32 take UD.

(check the valid from date of Inspection plan it must be prior to lot creation date.)

Regards

Sujit

Answers (1)

Answers (1)

Former Member
0 Kudos

Thanks & closed

Thanx

n k s