Dear All,

I never woeked with SA in R/3 or in APO but for this new project i need to work in SA in R/3 and APO.

Can you please guide how to start. I need to know the SA flow in R/3 and APO.

PLease suggest.

Thanks in advance

Amol

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Amol,

I have attached SAP link which will be a good starter to startwith

scheduling agreement scenarios in APO

http://help.sap.com/saphelp_scm70/helpdata/EN/86/705c1684178640a392d679a5285586/frameset.htm

Hope this will be more helpful to you.

Please confirm

Regards

R. Senthil Mareeswaran.

former_member928177
Participant
0 Kudos

Hi Senthil,

Thank you for your reply, i checked the link found that its more related to BI part of Sales scheduling aggrement.

I want the details in APO-R/3 side or any business scenario.

Thank you again,

Amol

0 Kudos

Hi Amol,

You better look at this link http://help.sap.com/saphelp_scm41/helpdata/en/c1/147a375f0dbc7fe10000009b38f8cf/frameset.htm

Basically Scheduling Agreements are transferred to APO as External Procurement Relationships.

As part of APO planning you will create Delivery Schedule lines which needs to be Released to R/3 for subsequent execution.

Well its not as simple as I mentioned in one line but the last time I saw / used it was 4 years back but the help documentation should be sufficient.

Hope this helps.

Somnath