on 07-29-2009 4:55 PM
Dear All,
I never woeked with SA in R/3 or in APO but for this new project i need to work in SA in R/3 and APO.
Can you please guide how to start. I need to know the SA flow in R/3 and APO.
PLease suggest.
Thanks in advance
Amol
Hi Amol,
I have attached SAP link which will be a good starter to startwith
scheduling agreement scenarios in APO
http://help.sap.com/saphelp_scm70/helpdata/EN/86/705c1684178640a392d679a5285586/frameset.htm
Hope this will be more helpful to you.
Please confirm
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amol,
You better look at this link http://help.sap.com/saphelp_scm41/helpdata/en/c1/147a375f0dbc7fe10000009b38f8cf/frameset.htm
Basically Scheduling Agreements are transferred to APO as External Procurement Relationships.
As part of APO planning you will create Delivery Schedule lines which needs to be Released to R/3 for subsequent execution.
Well its not as simple as I mentioned in one line but the last time I saw / used it was 4 years back but the help documentation should be sufficient.
Hope this helps.