I understand that there is a provision to create a validation under "Consistency Check project structure". If I create a validation here where shall I assign this (like if we create a Proj. defn or WBS validation, we can assign the same in the Proj. profile). I want this to be assigned in the similar way.
thanks in advance.
For consistency check in Project structure, the validation will not get activated directly.So you cannot default it in OPSA.
Such consistency check validations are used in transactions CNC4 & CNC5.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Did you check OPSI
REgards,
Pritam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vinvidh_1,
You need to assign the validation at project profile.
IMG-PS-Structures-Operative structures-WBS-Create Project profile (OPSA)
Select the project profile and open it in Control tab tehre is a screen area Valication: Project definition and WBS elements Mention your validation in the required filed select Automatic Validation.
Regards,
Praveen
Hi Praveen,
Thanks for your mail. Already I tried this. Actually, if we create a validation for Project, we will assign this in OPSA whereas I have created a validation under "Consistency check Project Structure" where to assign this validation as it is not appearing in OPSA when I use F4 for validation for Proj. def.. If I forcibly enter this, it gives a message, this validation is assigned to class 73 and not to class 70. How to proceed.
thanks
Vinodh