on 07-29-2009 10:42 AM
Hello gurus,
I will explain my scenario by following ex.
1. Suppose i have a requirement in Plant A of quantity 500.
2. Plant B has stock of 800 Q
3. But there is a outbound STO PR of quantity 500 from PLANT B to Plant C.
4. So, now when i run DRP, it is creating STO PR of quantity 500 from plant B to Plant A (actually it should not happen as there is already outbound STO PR.... point 3)
My question is how i can take into consideration STO PR... Means actual available quantity in plant B should be 800-500 = 300.
Its not happening currently.
How can i activate this? Is there any customisation related to this in Availability check or in plant parameters.
Plz. help
Navin
Edited by: Navin R. on Oct 30, 2009 5:34 AM
HI..
its DRP or MRP..?
what is outbound STO PR ??
Kindly provide more inputs and explain scenario in detail?
Thanks
Jinoy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
As explained in my earlier example.....
If there is a STO PR where
ex.
Supplying Plant is B - so for plant B it is outbound as stock is going out
Receiving Plant C - for plant C it is inbound as stock is coming in.....
so now look into my earlier example...u will understand it clearly....
and i m running DRP....BY Zprogram......to create STO pr and program is not considering the quantity of sto pr..
Please suggest...
thanks,
navin
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.