I will explain my scenario by following ex.

1. Suppose i have a requirement in Plant A of quantity 500.

2. Plant B has stock of 800 Q

3. But there is a outbound STO PR of quantity 500 from PLANT B to Plant C.

4. So, now when i run DRP, it is creating STO PR of quantity 500 from plant B to Plant A (actually it should not happen as there is already outbound STO PR.... point 3)

My question is how i can take into consideration STO PR... Means actual available quantity in plant B should be 800-500 = 300.

Its not happening currently.

How can i activate this? Is there any customisation related to this in Availability check or in plant parameters.

Plz. help

Navin

Edited by: Navin R. on Oct 30, 2009 5:34 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI..

its DRP or MRP..?

what is outbound STO PR ??

Kindly provide more inputs and explain scenario in detail?

Thanks

Jinoy

Former Member
0 Kudos

Hello,

As explained in my earlier example.....

If there is a STO PR where

ex.

Supplying Plant is B - so for plant B it is outbound as stock is going out

Receiving Plant C - for plant C it is inbound as stock is coming in.....

so now look into my earlier example...u will understand it clearly....

and i m running DRP....BY Zprogram......to create STO pr and program is not considering the quantity of sto pr..

Please suggest...

thanks,

navin