I need your help for this subject, Can plan cost of RA version for each WBSE be updated automatically when ever actual cost of this WBSE exceeds its plan cost.
Thanks,
Hend
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For the definition of valuation method in expert mode (t-code OKG3) check the Overrun indicator (value A).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In RA for respective RA version there is setting of valuation basis, in expert mode of valuation method of RA, through this you can control the picking of base value (planned cost/ actual cost based on condition like greater than.) for the complete RA calculation and its result.
Secondly there is plan version setting in the same expert mode screen, which is used for the determining the planned version with reference to actual/ planned RA calculation setting of RA version.
These setting helps in defining a base for RA calculation and its results but does not updates your planned cost.
I hope this will help you.
Regards
Avisek Bhardwaj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.