Hi,

My sale order having following items

1. x - 3 - schedule date - 20.08.2009

2.Y - 5 - Schedule date - 10.08.2009

3. Z - 6 - Schedule date - 03.09.2009

order i created yesterday but all these material are available today & I have to deliver it today only

but at the time of delivery schedule line error I am getting

& in Sales order also in schedule line tab for today's date confirmed quantity showing zero

so I told end user just check fix date & quantity tab after that system confirmed all the quantity.

In this case we need to go back in sales order & we have to do these changes

This should not happen how systems will confirmed order automatically ?

in VL01N which date we need to enter to avoid schedule line error?

Is it require to Enter storage location in shipping at the time of creating sales order?

Regards,

Akshay

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI,

Solution1 - Go to VA02 Transaction and Run availability check. As material avaialable it will confirm delivery qty

Solution2 - In VL01N Transaction enter Date - 03-09-2009 (Last schedule line date ) It would create delivery and you can process further i.e Picking and PGI.

Hope it would help.

Devendra

Answers (1)

Answers (1)

former_member1249468
Contributor
0 Kudos

Hi ,

Please run the availability check in sales order and check whetehr the quantity has been confirmed or not ,by going in to sales order--double click on line item - schedule linesconfirmed qty.If the quantity is confirmed then it will allow to proceed further.

Also check and remove if there are any blocks for schedule lines at line item level.

Hope it helps.