on 07-28-2009 7:32 PM
I understand that SLD 7.0 and 7.1 employ "automatic forwarding" that updates all data supplier targets with new system information. But, is there a nightly synchronization job between the master and slave SLDs that synchronizes technical systems between master and slave?
In our scenario, we supplied the wrong SLD user in the slave SLD which we assume is the reason why technical system synchronization from Master to Slave did not occur. Now, we need this information in the slave SLD but are unsure if a synch job will run nightly, daily, weekly, etc.
Hi
The SLD Bridge only send messages to the subscribers, when it get new data. So you could try to run RZ70 on abap systems connected to the master and see if it helps.
Regards
Daniel Graversen
[http://www.figaf.com]
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In 7.0 you can either use export/import to sync the content - if you use export line "LD" only the technical system data will be exported/imported, but you can also use export line ALL to export/import all SLD content (Content Repository, Landscape data, Namespaces and manuel entered data).
However the "automatic forwarding" will eventually update your target with ALL systems that functions as SLD datasuppliers, but yo have to wait until all data-suppliers has run.
BR
Tom Bo
User | Count |
---|---|
88 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.