Plan Driven Procurement in SRM 7.0

Former Member
0 Kudos

Hi SRM Friends,

I heard that in SRM 7.0 Plan Driven Procurement, leading PO is always created in Backend system.(Which means It is not supported by Extended classic). I am not sure if this is correct or not.

Please let me know if this is true as per standard out of Box functionality.

Thanks

Venkat

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks to Masa and Ashutosh for your answers.

Thanks

Venkat

Former Member
0 Kudos

Hello Venkat,

PDP is supported with both the scenarios as mentioned by Masa.

Some key points to consider:

1. Classic scenario: Inventory/ Account assignmnet as Blank, PR if transferred to SRM result in local PO (Direct material purchase behaviour)

2. Extended classic scenario: PO in SRM does not support the service hierachy.

Hope this helps.

Thanks

Ashutosh

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

Both Classic and Extended Classic can be configured in SRM 7.0.

Regards,

Masa