on 07-28-2009 5:39 PM
Hi,
When we have UC with multiple transports attached, it imports all transports at once and not in sequence. We want it to wait for earlier transport to finish and start next one. Is there any way we can resolve this issue?
Thanks,
Digesh
Yes
You can create mulitiple change documents attached to same support message using Create Change Document action
This will trigger multiple change document and in turn ur multiple Change request/UC which you can control by sending one by one using the action.
There is no other option because if you u create Task and keep the mulitple changes in the same request then it is imported at once.
Hope it solves ur problem
Regards
Prakhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Along the same lines, is there a way in Charm if you have UC with multiple transports, if one transport fails, the subsequest ones would not get imported ?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.