Dear SAPians,
We have cleared a Inspection Lot of Out Bound Delivery (OBD) by Mistake and now there is a need of cancillation / Rejection , so that material can not be dispatched. Please explain how is it possible??
Thanks in Advance.
Thanks for your inputs.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I assume that you have not gone PGI
then go to VL02n-->Shift +F2
this will cancel the OBD...this will not affect the inspection lot whcih you have cleared.
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Delete the Out Bound Delivery and Create a New Out Bound Delivery.
Best Regards,
K. Raghavendra Nayak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.