on 07-27-2009 4:51 PM
Hi Experts,
Iu2019m facing a problem while scheduling the project. When i schedule the project, the start date defined in project Def is copied to all WBS elementu2019s basic start date, wherein I wanted the dates to be determined based on the activity days.
Even in activity dates, the system is taking different date and donu2019t know on what bases and it is wrong.
I have connected each activity to predecessor and successor and also have given days, but still is get WBS plan dates wrong.
Under options Scheduling method is selected as Network determines dates, but still I did not succeed.
I'm using bottom up forward scheduling
Can some one tell me what I have missed and did wrong. I' also geting start date and end date as the same for WBS and activity, inspite od specifing the day for each activity
Thanks in advance,
Chandru
Edited by: Chandru Chandru on Jul 27, 2009 5:53 PM
Edited by: Chandru Chandru on Jul 27, 2009 5:55 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.