Capacity Check during production order creation

Former Member
0 Kudos

Dear All,

Could you advice please, how to setup a system in the way, to make automatical changes in dates of planned/production order based on capacity figures.

Thanks and Regards, Andrey

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

In Customizing of the availability check OPJk

  • whether the system should automatically trigger the capacity availability check during the order creation or order release

  • with which overall profile for the capacity availability check the system should work

o standard profile SAPSFCG013 for production orders and process orders

  • whether the system allows the conversion or release of an order in the case of insufficient capacity, or whether a user decision is necessary in order to do this

In Customizing of the shop floor control profile OPKP

(only relevant for the collective processing of production orders)

  • whether the system, in the event of insufficient capacity:

o executes finite scheduling

o confirms the capacity for the capacity requirements of the operations, that is, adds them to the basic load, thereby considering them during a future capacity availability check.

Hope it will serve for your purpose.

Regards,

R.Brahmankar

Answers (2)

Answers (2)

Former Member

andrey

to check th production capacity during order creation follow the steps below

1. goto opjk select the plant / order typr / business function

2. for cration u have business function normally as 1

3. select the function

4.check the contol indicator in capacity availlable check

5. if check indicator as selected for no checking remove thr indicator

Former Member
0 Kudos

Dear R Brahmankar,

Thanks for your answer,

then problem is solved.

regards, Andrey

Former Member
0 Kudos

Please, help me.

I did every you said, I have the same problem but when I create the production order, the order doesn't change the dates.

Thank you!

Former Member
0 Kudos

Hi Donald,

What is the process you are running?

Are you doing capacity check after production orders creation?

Regards,

Andrey

Former Member
0 Kudos

Thank you, Andrey.

Apparently yes.

Please help me, I need the order re-schedule dates & hours when the work centes are busy according their capacity.

Thanks