on 07-27-2009 7:24 AM
Dear All,
I am facing a problem while creating a inspection plan.
When I am trying to assign a resource to the inspection plan I am getting a message:
" Work center TEST RES plant 1500 does not exist for task list type Q"
Please advice.
Regards
Thanks, Raghu this was the issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just check the workcenter you have defined. Space would not be there for Workcenter.
Best Regards,
K. Raghavendra Nayak