Hi,

Is it possible to revoke or change the result recorded after UD is given and also stock posted for material.

In inspection plan i have activated the long term inspection check box for that particular MIC for which i want to change the results.

I have done UD reversal, stock reversal etc.

Then

I hv tried through QE02 but its showing:

Short term Inspection Completed.

All Insp.Completed.

UD has been Made.

pls suggest the possible solution on this.

Rgds,

Yogesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

How did you revoke the lot.

is it by active 08 or by SAP note.

Revert back

Regards

Sujit

Former Member
0 Kudos

Hi, Sujit,

I dont want to revoke the LOT but my query is How to record result after UD is given.

I have checked box for Long trem planning so that i can change results for required MICs.

Pls suggest.

Rgds,

yogesh Thorat.......

Former Member
0 Kudos

yes dear

I know you don't want to revoke the lot but

You have said: I have done UD reversal, stock reversal etc.

this is a reason I am asking you how did u did it so that i can help you.

Sujit

Former Member
0 Kudos

Dear sujit,

We have Ztcode developed for Stock posting reversal not for UD reversal.

Just want to know inspite of checking box for Long term planning in MIC also in Inspection plan.

Is there any provision for reentering results for already closed MICs.

User has made wong input entry while recording results.

Rgds,

Yogesh

Former Member
0 Kudos

Hi Yougesh,

To reverse the UD the User exit QEVA0008 may benefit you.

Apart from this kindly refer the SAP Note 175842 and 33924 .

Regards,

Shyamal

Former Member
0 Kudos

Hi

Once you have done result recording ....... even if the char is long terms & if you have forcefully completed the chars then even if char has LTIN status it will not allow you or it will not be treated as long term....so No RR correction can take place in this case.

I hope you got what I am saying

Regards

Sujit

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks a lot sujit for Ur rely.

Former Member
0 Kudos

Once UD is given Results Recorded cannot be changed if the MIC's defined are Short Term.

If you require to change the Results Recorded please mark the indicator Long Term Characteristics in MIC (QS23).

Best Regards,

K. Raghavendra Nayak