cancel
Showing results for 
Search instead for 
Did you mean: 

BOM Transfer

Former Member
0 Kudos

Hi,

I am trying to transfer a BOM from ERP to GTS system. I get the following message everytime I try to transfer

No definition of BOP evaluation exists for feedersystem ECCCLNT100

0 bill(s) of material were transferred to the GTS system successfully

I think it is not transfering the BOM to GTS. Any suggestions gurus?

Thanks,

Jennifer

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member58030
Active Participant
0 Kudos

You can also check your RFC connection

Regards, Prarit

Former Member
0 Kudos

This may seem basic, but always start at the beginning.

Check the BOM transfer logs in GTS (Risk Management Pref. Processing - Master Data) and in the feeder (transaction SLG1, Object /SAPSLL/BOM, Sub-Object /SAPSLL/BOM_R3. You might be able to determine the problem from the info there.

If not...

Make sure you have properly set up the plug-in to transfer BOMs (BOP stands for bill of product.)

If that is correct, check in GTS to be sure you have set up the legal reg for your agreement Country Group to Country Group. Then re-check the rest of the GTS config, and resend.

If all looks good, and you still get the error, and the logs don't help you, I usually sit with an ABAPer and run a trace on the transfer to determine if the problem exists in the feeder or in GTS and proceed from there.

Good luck!

Doug