Hi,

While creating the ARE-1, Our client is entering the Created on and Dispatched On dates in the Certification Dates tab.Somes somes he forget the Dispatched On dates.

He wants the Dispatched date as mandatory while saving the ARE-1.

How we can put it as a mandatory field?

Jyothi.

Edited by: jyothi. on Jul 24, 2009 9:09 AM

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Answered.

Former Member
0 Kudos

Hi

At the time of saving it wont ask but at the time of posting the ARE1 the system will prompt for removal time and posting date nothing but despatched date.

Else try with using a screen variaNT FOR J1ia101 t code in SHD0

regards

former_member312216
Participant
0 Kudos

Hi

I think you will have to add this field in the incompletion procedure inorder to make this field manditory

You cant make any field mandatory in sales order.

You can add that date field in incompletion procedure.

So before saving the sales document the system will give you a mess that sales order is incomplete.

And this will block your further procedure also unless and until you wont fill those entry.

So try to add that field in incompletion procedure Tcode OVA2, VUA2

revert if u have further doubts

regards

prashanth