on 07-23-2009 12:50 PM
Hi,
What is planiing segment?Where it used and How?Is it actually used or it is just concept?
Lalit
Hi
We can view the different Planning segments in MRP List (MD04/MD05) according to the planning types. The following segments are individually displayed and individually planned:
Net requirements planning segment : The net requirements planning segment is the part of the MRP list where the net requirements calculation is carried out at plant level during the planning run. (Ex Pln stg 10)
Gross requirements planning segment : The gross requirements planning segment groups together the gross requirements and the corresponding order proposals for gross requirements planning displayed separately (Ex Pln stg 11)
Storage location segment : A storage location segment is created for each storage location that is planned separately as well as the net requirements planning segment. In the storage location segment, the planned availability situation is displayed at storage location level (When planning using MRP areas)
Individual customer requirements planning : The segment for individual customer requirements planning displays the receipts and issues for customer requirements planning. A new segment is created for every individual customer requirement. (stg 20)
Planning without final assembly : The segment for planning without final assembly displays the requirements that are planned without final assembly. This, which means their procurement is triggered by the incoming sales orders and non-convertible planned sales orders with the order type VP. (Ex Stg 50)
If several segments are available in an MRP list, you can display them directly without having to search for them by scrolling. To do this, choose, Edit > Segments > Next segment
Regards
Brahmaji
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Refer this link for complete reference of planning segments
http://help.sap.com/erp2005_ehp_04/helpdata/EN/ed/d17fd7f52911d1a6bb0000e83235d4/frameset.htm
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
When you run MRP, the system considers Plant avaialble stock and all the requirements and receipts in it arriving at procurement qty and dates. In normal MTS scenario, the whole horizon is Planning segment.
In case of MTO, sales order there is a seperate segment and all the Net requirement caculation happens within this segment only. menas only the Stock of this segement is considered and only the requirements and receipts in this segment are consideed for Planning. you can see a seperate segment in MD04 seperated by Blue letters .
Similarly in PLanning startegy 11 also you have a seperate planning segment for GRP.
Hope this clarifies
Regards
Ratan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.